Monday, December 22, 2008

Project Holiday Remodel

So things are progressing nicely. All of the new electrical was completed and roughed in by Friday - 7 new circuits to the kitchen replacing good old knob and tube. Saturday was all about drywall - ceiling and walls are done along with the first coat of tape and mud. Progress... today - second coat, Friday - third coat. Weekend I'll tile the floor and put in the high hats. Then we wait for the cabinets to arrive.... tic toc tic toc....

I know.. pictures...

1 Comments:

At 10:43 AM, Blogger Chris said...

uh, you know - pictures? Well? Where are they?